Location: GROW AVENUE
(Wyatt Way to Shepard Way)
Restriction: One lane with flaggers
Duration: Through July
Contact: Dale Richards 206.307.3020
Reference: Grow Community; first phase of infrastructure development. (CP12-31)
Location: 278 WINSLOW WAY EAST
(The Winslow Mall)
Restriction: Sidewalk closure with pedestrian detour
Duration: May 16, 17 & 18 (W,Th & Fr)Contact: Dale Richards 206.307.3020 Reference: Roof beam replacement in ceiling of mall. (CP12-68)
Location: 4760 LYNWOOD CENTER ROAD
Restriction: One lane with flaggers
Duration: Through June
Contact: Dale Richards 206.307.3020 Reference: Infrastructure work for mixed use multi-family project across the road from Lynwood Center. (CP12-30)
Location: WINSLOW WAY at HWY 305
Restriction: intermittent pedestrian traffic interruption on northwest corner of intersection of Winslow Way & Hwy 305
Duration: Through September.
Contact: Dale Richards 206.307.3020
Reference: Island Gateway construction of two buildings requiring intermittent sidewalk closure. (CP12-41).
Location: MILLER RD
(Arrow Point Dr to New Brooklyn)
Restriction: One lane with flaggers
Duration: Through May
Contact: Fon Kuo 360.340.0849
Reference: Potelco project to replace 12 poles & existing 3-phase overhead wires & install anchor/guy wires over 1.4 miles.
Location: NEW BROOKLYN RD
(Sportsman Club to Miller Rd)
Restriction: One lane with flaggers
Duration: Through May
Contact: Josh Grenner 253.606.4745
Reference: Potelco system improvement project to replace 24 poles & setting a new span guy pole & tree trimming over 1.7 miles.